200-MW Shortfall Seen In Mindanao

The starvation of the province, Mindanao from electricity is in danger, suffering from another 200-megawatt (MW) shortfall for the succeeding years due to high demand and continues lacking of generation capacity.

It is said that the Department of Energy (DOE) is already banking on power charges and diesel-fired power plants to upsurge the available power in the region next year.

Energy Secretary, Jose Rene Almendras, mentioned that, “If we do not have additional generation in Mindanao by the dry season next year, we will have a shortage.”

“I am looking at least 100 MW, almost 200 MW. It also depends on the rainfall next year,” Almendras added.

Up to the present time, the hydroelectric power plant is responsible for 53 percent of the total power supply in Mindanao.

The Mindanao network, according to the National Grid Corporation of the Philippines, which is in need of at least an average of 1,300 megawatt (MW) during peak hours, lacked 50 MW to 300 MW, resulting in two to four hours of rotating blackouts in the first quarter.

“In Mindanao, the situation has significantly improved. What is being reported to us is that there are no more blackouts,” Almendras said.

As an update, last week, there was still no power outage in Mindanao which follows the completed repair of the 200 megawatt (MW) Pulangi IV hydropower plant in Bukidnon.

The DOE released a circular outlining effort last March needed from numerous government agencies and private firms to lessen power outages in Mindanao.

But, Almendras said that Mindanao is running on bare requirements and is without any emergency reserves. A failure in any of the power generation equipment will thus automatically result in a shortfall and blackouts.

Almendras said that the situation might worsen next year when demands increases and there is insufficient rainfall for the hydropower plants.

The DOE recommends that the resumption of operations and rehabilitation of the 100 megawatt (MW) Iligan diesel power plant and the rehabilitation and transfer of 120 megawatt (MW) of privately owned power barges, and the transfer to Mindanao of the 96 megawatt (MW) of power barges presently operated by National Power Corporation (NAPOCOR), in order to solve the power supply concerns.

The DOE is in talks with private firms for the transfer of several power barges, Almendras said.

The Commission on Audit (COA) review is ongoing regarding the Iligan plant issue.

“The COA has requested for some additional documents from the local government unit and from the bidder to substantiate their offer, their process and pricing,” Almendras said

The 100-MW plant, which was last operated in 2010, was sold to Alsons Consolidated Resources Inc. (ACR) subsidiary Conal Holdings Corporation after the local government acquired it due to tax delinquency.

However, the power plant also needs COA clearance before it can be sold to ACR and resume operations.

Almendras said that the DOE wants the plant to start operations within the year for it to reach the maximum capacity ahead of the dry season next year.

Lastly, DOE is reviewing its plans following the failed bidding of four 32-MW power barges of Napocor.

The bidding of the Power Sector Assets and Liabilities Management for the diesel-fired Power Barges 101-104 failed last week as only one of seven qualified bidders submitted an offer.

Under the bidding rules, winning firms should immediately transfer these power facilities to Mindanao and would have to stay there until 2014.

The DOE has been giving some warnings last 2010 with regards to Mindanao that it needs additional baseload generating capacity through private investor participation.

But the DOE said there were delays in securing permits from local government units.

For instance, Aboitiz Power Corporation, Sarangani Energy Corporation, and San Miguel Corporation are planning to put up coal-fired power plants in Mindanao but host communities opposed these plans due to environmental concerns.

3-hour rotating brownouts in Luzon start next week

Despite Energy Secretary Angelo T. Reyes’ brave pronouncements that Luzon will not be plunged into power supply shortages again, system operator National Grid Corporation of the Philippines (NGCP) warned Thursday of two-three hours of rotating brownouts hitting consumers in the country’s biggest grid for the next round if hurdles in generation deficiency cannot be addressed expeditiously.

The system operator declared ‘red alert’ status for the grid for almost a month, from February 16 to March 11, due to forecast deficiency in generation which may hover by as massive as 500 megawatts. When that happens, NGCP noted that the impact will be two to three hours of rolling brownouts.

Carlito C. Claudio, NGCP’s deputy assistant chief technical officer, said the power plants on inventory and which are scheduled to run while the Malampaya gas facility is on shutdown would not be enough to meet demand.

Claudio explained that the 600-megawatt Malaya thermal plant cannot run at full capacity “due to fuel constraints,” since the reserve fuel has already been used to offset capacity loss in the grid when Sual plant was on shutdown.

Read more>>